Realizations

transfer of an oversize machine for a German customer

At the request of our German contractor, we transferred the machine with a special transport. Due to the construction of Bosch aluminum profiles, the machine was slightly “slimmed”. The heaviest components were dismantled and transported separately.

The project included:
  • testing the machine together with the customer,
  • disassembly of parts of the device components,
  • strengthening the structure with additional profiles,
  • disassembly of electrical connections,
  • securing the machine and components,
  • transport to the destination,
  • insurance,
  • machine installation,
  • reassembling the machine and electrical connections.
  • commissioning with the customer.

electrical installation in the warehouse and in the office building

Execution of electrical and teletechnical installations at the facility of a plant producing metalworking machines.

The project included:

  • installation of cable routes,
  • installation of internal power supply cables,
  • installation of lighting wiring and sockets,
  • installation of basic and emergency lighting,
  • construction of new electrical switchboards and their assembly,
  • electrical and lighting measurements,
  • protection of fire crossings,
  • lightning protection system on the roof,
  • external lighting,
  • LAN logical cabling cat.6a,
  • installation CCTV,
  • alarm and access control installation.

Rebuilding shopping mall into hardware store

The overall project included the dismantling of the existing electrical and water infrastructure as well as walls and display windows. Then the hall was adapted to a new client – a hardware store.

The project included:

  • disassembly of the old electrical installation,
  • disassembly of water / sewage pipes,
  • disassembly of walls, sites, metal structures,
  • installation of new cable routes,
  • assembly of internal power supply,
  • installation of cabling for new lighting and collection points,
  • modification of existing electrical switchboards,
  • construction of new electrical switchboards,
  • reconstruction (practically from scratch) of two ATS systems,
  • fire protection infrastructure cabling,
  • electrical and lighting measurements,
  • protection of fire crossings,
  • lightning protection system on the roof,
  • external lighting.

wiring of shell drying machine

Wiring the machine in one of the factories near Zielona Góra.

At the client’s request, the cabling of the new machine was carried out, as well as connecting the cables to the switchboards and participation in start-up.

MACHINE TRANSFER FOR A POLISH FACTORY

Comprehensive relocation service for machines in an electronic components factory.

The project included

  • dismantling the window on the first floor of the building – at a height of 5m,
  • construction of a special platform in front of the window in order to take out the machines (the heaviest machine 4.5 tons),
  • the service of lifting machines by crane directly for transport,
  • transport to the destination,
  • positioning, leveling and start-up assistance.

Installation of medium voltage switchgears and transformers.

The work was carried out in a technical fiber factory.

The project included the installation of:

  • MV switchgear,
  • 2000kVA transformer,
  • 1600kVA transformer,
  • capacitor bank,
  • busbars between transformers and LV switchgear,
  • cables between the MV switchboard and transformers.

installation of cable routes on hEights.

Installation of cable routes on heights. Main switchboard. Power supply.

The project was implemented at the plant producing wood-like materials.

 

Relocation of machines from germany to poland.

Transfer of the complete production line from Munich (Germany) to Poland.

The project lasted 7 weeks (June-August 2019). It was implemented in three stages. The works were carried out in parallel at the place of disassembly and assembly of the machines (two separate teams).
 

Comprehensive implementation including:

  • disassembly of machines on site,
  • transport (12 lorries),
  • insurance,
  • equipment (forklifts, mobile platforms) at the place of disassembly and assembly,
  • assembly of machines on site including tests,
  • coordination of the entire project in English and German.

modernization in automotive industry.

Supply of switchgears in the Siemens Sivacon S8 system.

In one of the local companies from the automotive industry, we have completed quick weekend assembly and commissioning of Siemens switchboards.